Thursday, November 26, 2009
November Progress!!!
Last few weeks the builder done the below works -
Brick clean finished
Downpipes install finished
Electric rough finished
Air con rough finished
Ground Floor roof cover & eaves finished
Sunday, November 01, 2009
More Progress, however,Very SLOW!!
Last few weeks works goes very slow-
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor
: Cladding installed and painted
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor
: Cladding installed and painted
Tuesday, October 20, 2009
We have a roof over our heads!!!!
Thursday, October 08, 2009
Render Finished!!
Front render started on the 02/10/09, because of the rain, it takes longer, finally yesterday they have finished it.
Today, they have started the fascia, gutter and roof cover work!!!!
Today, they have started the fascia, gutter and roof cover work!!!!
Monday, September 28, 2009
Thursday, September 10, 2009
Tuesday, August 18, 2009
Subscribe to:
Posts (Atom)
































