Monday, December 14, 2009
December Updates!
Two weeks earlier Tyrells conducted the independent inspection. As per our SS, there is no major issue. Both Local and Tyrells inspections passed.
We have few updates!
:: Doors & Skirting Delivered & Installed
:: Kitchen & Vanities Supplied
:: Stairs Installed
:: Gyprocks Installed
Thursday, November 26, 2009
November Progress!!!
Last few weeks the builder done the below works -
Brick clean finished
Downpipes install finished
Electric rough finished
Air con rough finished
Ground Floor roof cover & eaves finished
Sunday, November 01, 2009
More Progress, however,Very SLOW!!
Last few weeks works goes very slow-
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor
: Cladding installed and painted
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor
: Cladding installed and painted
Tuesday, October 20, 2009
We have a roof over our heads!!!!
Thursday, October 08, 2009
Render Finished!!
Front render started on the 02/10/09, because of the rain, it takes longer, finally yesterday they have finished it.
Today, they have started the fascia, gutter and roof cover work!!!!
Today, they have started the fascia, gutter and roof cover work!!!!
Monday, September 28, 2009
Thursday, September 10, 2009
Tuesday, August 18, 2009
Sunday, August 02, 2009
Wednesday, July 29, 2009
Tuesday, July 28, 2009
SITE START!!
After getting the council approval, we need to finalise few docs like construction certificate, builder insurance and final approval from the bank!!!!
Builder inform us the site would be started on the 27/07/2009. However, 27th morning I received a phone call from our SS that, they are not able to start the work today because the neighbor builder did some bobcat our site. Immediately I contact the neighbor builder SS and he promise he would take care of that.
Finally Site work has started on the 28/07/2009.
Builder inform us the site would be started on the 27/07/2009. However, 27th morning I received a phone call from our SS that, they are not able to start the work today because the neighbor builder did some bobcat our site. Immediately I contact the neighbor builder SS and he promise he would take care of that.
Finally Site work has started on the 28/07/2009.
Tuesday, June 30, 2009
COUNCIL APPROVAL!
We received BASIX approval on the 24/02/2009 and lodge the application to Developer on the 10/03/2009, Developer need few changes in our landscape plan, setback our home few mm, etc and got the approval from them on the 29/04/2009 :(.
We lodge our application to council on the 30/04/2009 & received the council approval on the 29/06/2009.
We lodge our application to council on the 30/04/2009 & received the council approval on the 29/06/2009.
Subscribe to:
Posts (Atom)