Our build is almostcompleted. We need some touchup work like kitchen bulkhead need to be painted, builder painted few places with wrong colour.
Stairs
Monday, March 01, 2010
Sunday, January 31, 2010
Tuesday, January 19, 2010
January Updates!!!!!
Hi Guys
As from 22-Dec-2009 to 26-01-10 is the industry shutdown period. We don't have much update.
We have few updates-
:: Skirting & Architrave done
:: Waterproofing done
:: Tiles in wet areas done
:: Painting started
Regards
As from 22-Dec-2009 to 26-01-10 is the industry shutdown period. We don't have much update.
We have few updates-
:: Skirting & Architrave done
:: Waterproofing done
:: Tiles in wet areas done
:: Painting started
Regards
Monday, December 14, 2009
December Updates!
Two weeks earlier Tyrells conducted the independent inspection. As per our SS, there is no major issue. Both Local and Tyrells inspections passed.
We have few updates!
:: Doors & Skirting Delivered & Installed
:: Kitchen & Vanities Supplied
:: Stairs Installed
:: Gyprocks Installed
Thursday, November 26, 2009
November Progress!!!
Last few weeks the builder done the below works -
Brick clean finished
Downpipes install finished
Electric rough finished
Air con rough finished
Ground Floor roof cover & eaves finished
Sunday, November 01, 2009
More Progress, however,Very SLOW!!
Last few weeks works goes very slow-
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor
: Cladding installed and painted
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor
: Cladding installed and painted
Tuesday, October 20, 2009
We have a roof over our heads!!!!