Tuesday, May 04, 2010

PCI Done!!!!!

Hi Guys

We just have finished our PCI, no major defect. Most of them are paint touchup and few window frame and glasses are scratched. Our private inspector also pick few incompleted and poor quality work like no seal on top n bottom of the main entrance door and laundry door, poor quality render work and crack on few places on render, few places grouting is not completed.

Handover will be two weeks after PCI. Finger crossed, everything will be as per plan.

Regards!

Monday, March 01, 2010

Few more photos!!!

Linen cupboard

Front Entry door

Kitchen

Foyer

Just waiting for the PCI!!!!!

Hi Guys!!!!
Our build is almostcompleted. We need some touchup work like kitchen bulkhead need to be painted, builder painted few places with wrong colour.

Stairs

First floor rampus area

Main bathroom vanity

Main bathroom with semi-framed shower screen

Ensuite with frameless shower screen

Sunday, January 31, 2010

More January Update!

Kitchen

Kitchen

Bathroom

Ensuite

Ensuite

Tuesday, January 19, 2010

January Updates!!!!!

Hi Guys
As from 22-Dec-2009 to 26-01-10 is the industry shutdown period. We don't have much update.

We have few updates-
:: Skirting & Architrave done
:: Waterproofing done
:: Tiles in wet areas done
:: Painting started

Regards

Monday, December 14, 2009

December Updates!

Front entry door

Gyprocks inside garage

Gyprocks


Gyprocks

Two weeks earlier Tyrells conducted the independent inspection. As per our SS, there is no major issue. Both Local and Tyrells inspections passed.

We have few updates!

:: Doors & Skirting Delivered & Installed
:: Kitchen & Vanities Supplied
:: Stairs Installed
:: Gyprocks Installed

Thursday, November 26, 2009

November Progress!!!


Front with first floor balcony


Street view from the first floor balcony

Ground floor roof

Kitchen splashback


Electric rough


Air con rough

Last few weeks the builder done the below works -

Brick clean finished
Downpipes install finished
Electric rough finished
Air con rough finished
Ground Floor roof cover & eaves finished

Sunday, November 01, 2009

More Progress, however,Very SLOW!!

Front Render painting started not yet complete

Front Cladding painted

Eaves installed and painted

Cladding painted

Last few weeks works goes very slow-
As per the SS plan the Tyrell’s independent quality inspection should be on two weeks earlier, however not yet schedule for it.
: Brick cleaned partial
: Eaves installed & painted first floor
: Downpipes installed and painted first floor

: Cladding installed and painted

Tuesday, October 20, 2009

We have a roof over our heads!!!!






Our roof has been completed last week (16/10/2009). First floor wall cladding is going on. Hopefully, cladding will be finishing end of this week.

Thursday, October 08, 2009

Render Finished!!









Front render started on the 02/10/09, because of the rain, it takes longer, finally yesterday they have finished it.

Today, they have started the fascia, gutter and roof cover work!!!!

Monday, September 28, 2009

MORE BRICKS!










Last Friday, our SS informed us that today our brickwork is going to finish!

Thursday, September 10, 2009

Tuesday, August 18, 2009